|   |
Cumberland Trail
Bridges |
  |
Bridge construction is an integral part of building the Cumberland Trail. The bridges on the Cumberland Trail are of two basic designs ---- simple pole bridges and suspension bridges.
|
A natural wood pole bridge:
Handrail Construction:
Turkey Creek Bridge - under stringer outrigger handrail
Natural wood pole bridges: Roofing tar and gravel surfacing: Applying roofing tar and creek gravel to canted surface "Canting": "Canting" a log to use as a bridge stringer using a hand axe Completed natural wood bridge:
Completed natural wood bridge over Greens Branch
Pole bridge piers: Rock Piers: A typical rock pier with the sill in place "Log Cabin" Pier Construction: The "log cabin" pier on the Turkey Creek Bridge
"Skyline" Construction Method of Setting Stringer Logs/Poles Natural Pole: Setting the natural wood stringer for Greens Branch Treated Pole: Setting the 28 foot treated pole stringers for Turkey Creek
Anchoring Stringers: Drilling stringers for rebar: Using a brace and bit to drill through stringer and into sill
Suspension Bridges: Suspension Bridges currently in design phase: |
OBED BRIDGES
All four sills will be five foot long and 10" min diameter. The 4'-6" diameter center pier should be approximately 6'-0" height to the top of the sill (less than 5 ft to the top of the rock). Note that this will still be our tallest rock pier to date. Rock availability is great near the bridge site.
The north and south sills will be anchored to the stringers and the soil with 1/2" (#4) rebar driven 3 foot, or until hitting rock, whichever occurs first.
Troy's bridge design and construction plan have been entirely approved by the Boy Scouts, and constuction started on December 30, 2002. Troy met with representatives from the Nashville Electric Service and they agreed to not only donate the telephone poles , but to also delivered them to the spot where needed on December 30. We owe Troy and Nashville Electric Service a big thanks for their help!! Completion in early spring is anticipated.
This is a front-country bridge. The Eagle Scout Bridge is less than 100 yards from the road. A double span is required. The main span is an 18'-0" utility pole construction with a 3 foot tread width and double
handrail is required. The decking should be 2 x 6's with a "top" outrigger construction. The main span utility poles should be a minimum of 7" diameter on the small end. The 10'-0" long ramp span poles should be a minimum of 6" diameter. A handrail is required on the downstream side of the ramp span.
LITTLE SODDY BRIDGES
This is a front-country bridge. The Trailhead Parking Bridge is less than 100 yards from the road. A 35 foot utility pole construction with a 3 foot tread width and double
handrail is required. The decking should be 2 x 6's with a "top" outrigger construction. The utility poles should be a minimum of 10 1/2" diameter on the small end. Four foot
long sills of 10" min diameter will be required. The 4'-0" diameter
NW pier should be approximately 3'-0" height. The 4'-0" diameter Southeast pier should be approximately 2'-0" height.
This is a back-country bridge. The bridge is less than 100 yards downhill from vehicle access via Hotwater Road. A 27 foot utility pole construction with a
2'-8" tread and a handrail on the downstream side will be required. The decking should be 2 x 6's with a "top" outrigger construction. The utility poles should be a minimum of 8
1/2" diameter on the small end. Four foot long sills of 10" min diameter will be required.
The sills will be anchored to the stringers and the soil with 1/2" (#4) rebar driven 3 foot, or until hitting rock, whichever occurs first.
This is a back-country bridge. The bridge is less than 100 yards downhill from vehicle access via Hotwater road. A 23 foot utility pole construction with a
2'-8" tread and a handrail on the downstream side will be required. The decking should be 2 x 6's with a "top" outrigger construction. The utility poles should be a minimum of 8"
diameter on the small end. Four foot long sills of 10" min diameter will be required.
The sills will be anchored to the stringers and the soil with 1/2" (#4) rebar driven 3 foot, or until hitting rock, whichever occurs first.
This is a back-country bridge. The bridge is less than 100 yards downhill from vehicle access via Hotwater Road. A 22 foot utility pole construction with a
2'-8" tread and a handrail on the downstream side will be required. The decking should be 2 x 6's with a "top" outrigger construction. The utility poles should be a minimum of 8"
diameter on the small end. Four foot long sills of 10" min diameter will be required.
The sills will be anchored to the stringers and the soil with 1/2" (#4) rebar driven 3 foot, or until hitting rock, whichever occurs first.
BOARD CAMP BRIDGES
A 120 foot true suspension bridge with an 80 foot long 3'-0" deck will be required. Poles to
carry the suspension cable sag will not be required due to the location of bread truck sized and solid anchoring rocks above a good trail access shelf on each side. I discussed this bridge with John Graves and Jeff Brown -- TVA Civil Engineers with trail bridge design and construction experience --- and they will review our design and help us with the eye bolt anchoring design. They have also had experience "bundling" smaller main suspension cables as we had discussed to avoid having to handle heavy and stiff 1" cable.
This is a back-country bridge. The bridge is less than 50 yards downhill from vehicle access via an old mining road. An 18 foot utility pole construction with a
2'-8" tread and a handrail on the downstream side will be required. The decking should be 2 x 6's with a "top" outrigger construction. The utility poles should be a minimum of 8"
diameter on the small end. Four foot long sills of 10" min diameter will be required.
The sills will be anchored to the stringers and the soil with 1/2" (#4) rebar driven 3 foot, or until hitting rock, whichever occurs first.
This is a back-country bridge. The bridge is less than 100 yards downhill from vehicle access via an old mining/logging road. A 12 foot utility pole construction with a
2'-8" tread and a handrail on the downstream side will be required. The decking should be 2 x 6's with a "top" outrigger construction. The utility poles should be a minimum of 7"
diameter on the small end. Four foot long sills of 10" min diameter will be required.
The sills will be anchored to the stringers and the soil with 1/2" (#4) rebar driven 3 foot, or until hitting rock, whichever occurs first.
This is a very scenic back-country bridge with very difficult access. Approximately 80 yards up a 40 degree rocky slope on the south side, and up an approxmately 100 foot vertical rock bluff, and
approximately 50 feet into the Bowater pine plantation........there is supposed to be a jeep road
that is accessible through private property. This access is currently being researched. The hike in from the north takes about an hour over difficult terrain.
This is a back-country bridge. Access is difficult except by 4-wheeler or very high clearance
4- wheel drive along an old mining road aproximately 70 yards from the bridge. A 32 foot natural bridge
construction will be required. A suitable white oak and a suitable black oak were identified nearby for
the stringer logs.
The oak log stringers should be a minimum of 12" diameter on the small end to allow a maximum of 4" to be removed in canting. 9" of wood must remain after canting. 4'-0" treated wood sills of 8" diameter will be required on each side. A
3 inch deep 5/8 inch hole will be required on each upstream side for a 3/8 inch eye bolt to be anchored in with anchor cement. 1/4 inch steel cable with clamps will prevent the sills and stringers from easily sliding off the rocks on both ends.
BIG SODDY BEAR HOLE CROSSING
Current plans are to finalize the bridge location once arrangements have been made with the engineering team to inspect the site.
This is a very scenic back-country bridge at a beautiful swimming hole with very difficult access.
The 200 foot span will require a suspension bridge. The anchoring design is challenging and
will require an engineering team experienced in suspension bridge anchoring to rock.
Steel towers or creosote poles will be required in order to handle the sag required for the true
suspension bridge. This bridge will be very similiar to the Suck Creek suspension bridge.
BIG AND LITTLE POSSUM CREEK BRIDGES
Current thinking is that this site may be better served with a 58 foot suspension bridge. Also, another site approximately 500 foot upstream is being reviewed. A decision will be made in late January.
If the current review of a potential suspension bridge or bridge relocation do not seem the best way to go, then a 30 foot utility pole construction with a 2'-8" tread and a handrail on the downstream side will be required. The decking should be 2 x 6's with a "top" outrigger construction. The utility poles should be a minimum of 9" diameter on the small end. A 3'-0" high 4'-0" diameter rock pier with a 4'-0" long sill of 10" min diameter will be required on the south side.
A 7'-0" high welded angle iron tower will be required on the
north side. The tower will be anchored with at least 8 each expansion type anchors to the rock which tips at approximately 40 degrees into the creek. Metal shims will be needed to compensate for the irregular
surface of the rock. A 2 x 6 treated wood covering will help the metal tower blend in with the enviroment.
The tower anchoring design will be reviewed by Jeff Brown and John Graves.
This is a back-country bridge. Recent surveys after heavy rains have changed this design to a suspension bridge. The bridge is approximately 100 feet downhill from vehicle access via jeep road. The preliminary suspension bridge design is currently underway.
A very beautiful loop trail from the main trail will bring the hiker to an old railroad crossing. Even
during high water this location can be easily and safely forded. We inspected this scenic site after a
big rain and determined that we would not recommend a bridge for this site. Safely and easily forded under most conditions, but NOT during very high water conditions.
This is a back-country bridge. The bridge is adjacent to a jeep road.
There was no good location for a bridge, but a great ford. The shady low sand and clay banks are lined with stately old hemlocks. Rocks to build the high piers needed along the damp banks were non-existant.
It would be also necessary to remove approximately 2-3 feet of soil on both sides in order to place the pier foundations on good rock. The span would be 55 feet.
This is a back-country bridge. Current thinking is a 45' natural pole bridge, with 4 to 5 ft piers dug &
tied to rock within the 20 yr flood plain. This may change as a result of the January site review.


RETURN TO MAIN PAGE