Big Dig 2015
For the first time in eleven years, the Cumberland Trail Conference conducted another Big Dig. The concept was to rally a sustained volunteer effort to build a specific section of trail. Big Dig 2015 officially ran from September 15, 2015 to October 25. But work began three weeks earlier. Long disused logging roads had to be cleared enough to allow access to the trail building area.
Working in conjunction with Cumberland Trail State Scenic Trail personnel, a general trail design concept was agreed on for a seven mile work area. Big Dig 2015 was focused on extending the 14 mile Daddy’s Creek Segment south from Devil’s Breakfast Table.
Box Score
Total Finished Trail Built: 10, 780′
Volunteer Hours: 820
Crew Hours: 388

Flags mark intended trail alignment
After a botanical, wildlife and archaeological survey and, clearance from the Cumberland Trail State Park, trail designers from the Cumberland Trail Conference began scouting and designing the alignment of the trail.
When ground conditions allowed, work was expedited with the use of a machine called a Skid-Steer. The machine roughs up the ground in the trail corridor making it easier for crews to dig down to soil suitable for a firm trail tread.
The Big Dig work week was Thursday through Sunday. The paid seasonal trail crew worked all four days and was joined by volunteers nearly every day. The schedule was arranged to allow volunteers who work during the week plenty of opportunities to participate.
Volunteer Participation is Critical. Some days two people showed up. Other days ten volunteers found their way to the work site. Overnight accommodations were made available at the near by Eden Ridge Missionary Retreat. Some volunteers came from more than 100 miles away.
As seen in the Box Score above, volunteer participation continues to be critical for construction of the CT.
Volunteers put in nearly two and a half times the work hours as the paid crew.
The number is actually higher since a dozen volunteers also worked in the weeks before the official start of Big Dig to clear brush and blow-downs from old logging roads needed to get workers closer to the dig sites.